The first phase of a planned transboundary renewable corridor began commercial export this month, sending power from a 3.2-gigawatt solar array across two new transmission lines into three provincial grids.
Construction of the array itself took under two years. The transmission lines took six, and that ratio is the most instructive number in the project.
Generation was never the constraint
Module costs have fallen far enough that the panels are among the cheapest components of a project like this. Land acquisition, grid connection agreements and the transmission build now dominate both the timeline and the budget.
Planners describe the same pattern across the region: a queue of approved generation projects waiting years for a connection that does not yet exist.
Curtailment and the storage question
Early operating data shows meaningful curtailment during the middle of the day, when output peaks and provincial demand does not. Two battery installations are under construction to absorb some of it, though at a scale that addresses hours rather than seasons.
- Peak output arrives several hours before peak demand.
- Battery capacity currently covers a fraction of the daily surplus.
- Long-duration storage remains at pilot scale everywhere in the region.
What the provinces actually bought
The offtake agreements are structured around firm delivery windows rather than raw megawatt-hours, which pushes the intermittency risk back onto the operator. It is a harder contract to sign and a more honest one.
The transboundary complication
Exporting electricity across a border raises questions that exporting goods does not: who is liable when a fault propagates, whose regulator sets the frequency standard, and how the carbon accounting is split between generator and consumer.
Those questions are being settled bilaterally, corridor by corridor. A regional framework has been discussed for a decade without arriving.
What comes next
Phase two would roughly double capacity and add a third transmission route. Its financing depends on whether the first phase’s curtailment numbers improve once the batteries come online this winter.